Whether the solvent liquefaction recovery unit can give full play to the design effect, in addition to the scheme itself, the on-site installation and commissioning are equally critical. Wrong connection of pipeline, reversal of refrigerant flow direction and uncalibrated control parameters will cause abnormal performance of the device at the initial stage of operation. LuoyangWohong PetrochemicalEquipment Co., Ltd. provides on-site installation guidance, system debugging and operation training services after the equipment is delivered to help the user's operation team to turn the device on and off as soon as possible.
The training is aimed at the operation team and equipment management personnel, and the content is carried out according to the three levels of "understanding, operation and judgment": which tables to look at during daily inspection, which numerical deviations indicate what, and which valve to move first in case of frost or abnormal liquid level. In the training, the actual parameters of this debugging will be used as examples to make the operators have an intuitive understanding of the response law of the device.
| Segment | Main content | Delivery Output |
|---|---|---|
| Installation Guide | Position, connection and instrument confirmation | Installation Self-Test Checklist |
| System debugging | Single machine, airtight, cold state, with material | Commissioning record and parameter table |
| Operation training | Inspection, regulation and abnormal judgment | Operation card and training record |
| Tracking Services | Return visit and parameter review at the initial stage of operation | Operational recommendations |
Q: Is the installation and commissioning service remote or on-site?
Answer: On-site service is given priority to. On-site cooperation is required in the installation and commissioning of materials. Daily problems after commissioning can be quickly responded to through remote communication.
Q: Can the user's own installation team undertake the installation?
Answer: Yes, it is possible. We provide drawings, technical requirements and installation self-inspection list, and guide key processes on site according to the agreed nodes.
Q: How long is the debugging cycle in general?
Answer: It is related to the scale of the device, site conditions and supporting conditions of public works. The scheduling node will be given in the scheme stage, and the actual site progress shall prevail.
Q: Is the training only done once?
Answer: System training will be conducted during the first operation, and special training can be arranged for subsequent personnel adjustment or device modification.
Luoyang wo hong petrochemical equipment co., ltd. focuses on condensation and membrane separation VOCs organic solvent liquefaction recovery unit, providing complete services from scheme design to installation, commissioning and operation training. Welcome to call exchange.