VOCWaste gas treatment equipmentFrom factory production to formal operation, the entire cycle is influenced by factors such as equipment specifications, site conditions, and installation complexity. Here are rough cycle references based on different processes.
activated charcoalAdsorption equipment is the simplest type. After the equipment leaves the factory, the transportation time is usually one to three days. After arrival, the installation workload is very small, mainly to place the equipment, connect the inlet and outlet ducts and power supply, usually completed in half a day to a day. Debugging is also very simple. After powering on, check the direction of the fan and adjust the air volume. Half a day is enough. It usually takes one to two days from the arrival of the equipment to its operation.
Catalytic combustion equipment is slightly more complex. The transportation time is one to three days. After arrival, the host needs to be placed in place, connected to the air ducts, gas pipelines, power lines, and signal lines, and the installation time is usually two to three days. Debugging includes burner ignition testing, temperature control calibration, interlock protection verification, etc., which takes one to two days. From arrival to operation, it usually takes three to five days.
Thermal storage oxidation equipment has the longest installation cycle.RTOThe equipment has a large volume and weight, and may require special vehicles for transportation, which takes two to five days. After arrival, it is necessary to lay the foundation, hoist it in place, connect large-diameter air ducts, install chimneys, lay gas pipelines and electrical circuits, and the installation time is usually five to ten days. Debugging includes blowing the thermal storage ceramic body, burner debugging, timing adjustment of switching valves, system linkage testing, etc., which takes three to five days. From arrival to operation, it usually takes ten to fifteen days, and larger projects may take longer.
The installation cycle of membrane condensation recovery equipment is between activated carbon and catalytic combustion. The equipment adopts a modular design, and the internal pipelines and electrical connections have been completed before leaving the factory. The transportation time is one to three days. After arriving, simply place the equipment in place, connect the inlet and outlet ducts, power lines, and cooling water pipes. If necessary, it usually takes one to two days to complete. Debugging includes cooling system testing, vacuum system testing, and automatic control parameter setting, which generally takes one to two days. From arrival to operation, it usually takes three to five days.
It should be noted that the above cycle is estimated based on the premise that the on-site conditions are met. If on-site preparation work such as equipment foundation, renovation of air ducts, and capacity expansion and distribution is required, the cycle will be correspondingly extended. It is recommended to complete on-site preparation work in advance before the equipment is shipped, which can greatly shorten the time from arrival to operation.
LuoyangWohong PetrochemicalThe membrane condensation recovery equipment produced by Equipment Co., Ltd. adopts a modular integrated design, which completes all assembly and testing before leaving the factory. The on-site installation workload is small and can be quickly put into operation. The company is located in W2-1, Dongda Science and Technology Industrial Park, Luoxin Industrial Agglomeration Zone, Xin'an County, Luoyang City, with the website www.wohongshihua.com.