The installation of the device is only the beginning. Whether the design effect can be stably run depends on whether there is an operation procedure that can be understood and used on site, and whether there is a team that can really operate. The solvent recovery device involves several specialties of refrigeration, vacuum, heat exchange and solvent storage. If the operation is improper, the recovery rate will not go up; if the operation is improper, it will trigger interlocking shutdown and even bring potential safety hazards. LuoyangWohong PetrochemicalThe equipment shall be provided with preparation of operation procedures and operation training services in the delivery process, and the control logic, start and stop sequence, daily inspection points and abnormal handling methods of the equipment shall be organized into documents and training contents that can be directly executed on site.
Training should be separated by post to avoid pulling everyone to the same set of content-operators can't remember maintenance details, and maintenance workers don't care about each shift's record sheet.
The total amount of content after separation is actually less, because each post only needs to master the part related to itself. Training is also easier to assess.
The operating procedures are not excerpts from the equipment manual, but focus on translating the manufacturer's technical requirements into steps that can be performed on site. For example, the control of the condensation temperature is written as recording the outlet temperature of the condensation section every two hours, and in what order to deal with it when it exceeds the set value-so that the operator knows exactly what to do.
When writing, it is best to let the front-line operators participate in a round. If the inspection route, valve position and record form format written in the regulations are inconsistent with the actual situation on site, no one will implement the documents again.
Divide chapters by user so that everyone can quickly find what they want to see.
| Chapter | Main content | User |
|---|---|---|
| Device Overview | Process flow, main equipment and their respective roles | All staff |
| Driving steps | Check items, start sequence and judgment of reaching stable state | Operation team |
| Normal operation | Range of control parameters, inspection points and recording requirements | Operation team |
| Parking steps | Different disposal of normal parking and emergency parking | Operation team |
| Exception Handling | Common alarm causes and processing sequence | Operation team |
| Maintenance | Maintenance period, items and replacement of wearing parts | Maintenance personnel |
| Safety Points | Solvent storage, hot work, protection and emergency | All staff |
No. The control parameters and safety requirements of different solvents, different working conditions and different equipment are different, and the procedures must be compiled according to the actual device. The template of other projects is applied, and the site often cannot be implemented.
Depends on device complexity and personnel base. Usually, the theory and practical operation are arranged for several days, and then it is suggested to leave a period of training so that the team can run the steps smoothly in normal operation and solve the problems on the spot.
The procedure documents are left on site, and the new employees can master the basic operation according to the documents. If supplementary training is needed, on-site or remote support can be arranged.
This article is organized by Luoyang wohong petrochemical equipment co., ltd. the company provides design, manufacturing and operation and maintenance services for condensation recovery, membrane separation recovery and complete solvent recovery units for chemical and pharmaceutical enterprises. if you need process evaluation or scheme configuration, please contact and exchange.